OMG UM0-200 exam will get as a single OMG UM0-200 PDF or complete OMG UM0-200 testing engine as well as over 1000 other technical exam PDF and exam engine downloads. Tired of choosing OMG UM0-200 Configuration and Maintenance Exam material for preparing your OMG https://www.pass4itsure.com/um0-200.html exam, just come to Flydumps OMG UM0-200 exam sample questions page for all the real Q&As. Flydumps Cisco experts and specialists have created 84 real OMG UM0-200 exam Q&As for your learning. More, with our customers’ feedback, we have helped many candidates pass OMG UM0-200 exam easily.
QUESTION 1
In the exhibit, if the incoming arrows provide three control values, how many control
values are provided to the outgoing arrow?
Exhibit:
A. none
B. one
C. two
D. three
Answer: B
QUESTION 2
What does via foo in the exhibit designate?
Exhibit:
A. the sending of a foo message on the transition
B. transient pseudostate named foo
C. a transition terminating on the foo entry point
D. a Boolean guard equal to the logical value of foo
E. an action foo associated with the transition
Answer: C QUESTION 3 Assume component A provides an interface P and requires an interface R. In order for a component B to be substituted for component A, what must be true?
A. The interface that B requires must be type conformant with respect to the interface that A provides.
B. The interface that B requires must be type conformant with respect to the interface that A requires, and the interface that B provides must be type conformant with respect to the interface that A provides.
C. The interface that A requires must be type conformant with respect to the interface that B provides.
D. Components must be related to each other via a dependency.
Answer: B
QUESTION 4
What symbol depicts a CallBehaviorAction?
Exhibit:
A. A
B. B
C. C
D. D
E. E
Answer: E
QUESTION 5
What situation results from performing a CreateObjectAction on an abstract class?
A. undefined behavior
B. arbitrary object of one of its subclasses being created
C. exception being raised
D. error log entry being created
E. object of the specified class being created
Answer: A
QUESTION 6
What is NOT true about a roles and role bindings?
A. A role binding is an association.
B. A role binding maps a connectable element to a role in a collaboration occurrence.
C. The same object may play roles in multiple collaborations.
D. A role typed by an interface specifies a set of features required by a participant in a collaboration.
E. The same connectable element may be bound to multiple roles in a single collaboration occurrence.
Answer: A
QUESTION 7 What is implied when a transition terminates on the outer border of a composite state that has an initial and a history pseudostate?
A. The outgoing transition from the final pseudostate is taken.
B. The state is not entered.
C. The outgoing transition from the initial pseudostate is taken.
D. The outgoing transition from the history pseudostate is taken.
Answer: C
QUESTION 8
What stereotype notation is NOT correct?
Exhibit:
A. A
B. B
C. C
D. D
Answer: D.
QUESTION 9
In a state machine, what is true for a “do” activity of a state?
A. starts executing when the state is entered
B. specifies a condition that must always be true when the state is active
C. can only appear in a composite state
D. executes repeatedly as long as the state is active
E. is equivalent to an entry action of a state Answer: A
QUESTION 10
What is the notation for gates?
A. circular disc at the interaction frame
B. small arrow either into or out from the fragment frame
C. point on the fragment frame with an optional name
D. small rectangle on the fragment frame with associated name
Answer: C
QUESTION 11
What represents the deployment target of a deployed artifact?
A. the location of the deployed artifact
B. a shared aggregation relationship
C. a node instance, but never a property instance
D. the deployed artifact’s output data stream
Answer: A
QUESTION 12
Which is true of a provided interface associated with a port?
A. identifies the services that the object owning the port expects of objects connected via that port
B. represents an interface that must be defined within the classifier that owns the port
C. represents an interface that must be defined in the same package in which the classifier owning the port is defined
D. identifies the services that the object owning the port can offer to other objects connected via that port
Answer: D
QUESTION 13
Which list contains only connectable elements?
A. behavior, connector end, and port
B. behavior, port and property
C. port and connector end
D. connector end, port and part
E. property, port, and parameter
Answer: E
QUESTION 14
What situation results from performing a CreateObjectAction on an abstract class?
A. arbitrary object of one of its subclasses being created
B. object of the specified class being created
C. undefined behavior
D. error log entry being created
E. exception being raised
Answer: C
QUESTION 15
What most accurately describes the semantics modeled by the exhibit?
Exhibit:
A. HeaderGenerator and LineItemGenerator are Invoicer ports.
B. An Invoicer component is composed of a HeaderGenerator component and a LineItemGenerator component.
C. HeaderGenerator and LineItemGenerator realize Invoicer.
D. Invoicer realizes HeaderGenerator and LineItemGenerator.
Answer: C
QUESTION 16
Where is an interaction constraint placed?
A. either on the top of an operand or at the bottom of an operand
B. always at the top of an interaction
C. above the first event within an interaction operand
D. directly outside the combined fragment
Answer: C
QUESTION 17
What does a run-to-completion processing for state machines mean?
A. No other event will be processed until the current event is fully processed.
B. The thread executing the state machine cannot be pre-empted by the scheduler.
C. The executions of orthogonal regions are serialized.
D. Interrupts are disabled while the state machine is running.
Answer: A
QUESTION 18
What situation results from an ApplyFunctionAction?
A. reads objects and produces output values
B. produces output values
C. writes objects and produces output values
D. reads objects, write objects, and produces output values
E. performs any set of UML actions
Answer: B
A. r can be sent whenever p has been sent.
B. Whenever q and p have been sent, r can be sent.
C. There are legal traces according to Mcritical where r is absent.
D. The reception of p must precede sending of r.
Answer: D
QUESTION 20
Assume that !p means sending message p and ?p receiving it. In the exhibit, what is true
about Mneg?
Exhibit:
A. <!p, !q, ?p, ?q> is an invalid trace according to Mneg.
B. Neither p nor q should be sent between a and b.
C. p and q should not be sent concurrently from a to b.
D. <!p, ?q, ?p, !q> is an invalid trace according to Mneg.
Answer: A
QUESTION 21
What is true of a completion transition?
A. is executed when the state machine is terminated
B. is only triggered by a completion event
C. has no trigger defined
D. is executed when the final state is reached
Answer: B
QUESTION 22
What is the meaning of a required extension?
A. An instance of the extending stereotype must always be linked to an instance of the extended metaclass.
B. This extension has a higher priority than the other defined in the same profile.
C. An instance of the extending stereotype must never be linked to an instance of the extended metaclass.
D. The extension must be applied at least once in a model. Answer: A
QUESTION 23
What most accurately describes the semantics modeled by the exhibit?
Exhibit:
A. HeaderGenerator and LineItemGenerator realize Invoicer.
B. An Invoicer component is composed of a HeaderGenerator component and a LineItemGenerator component.
C. Invoicer realizes HeaderGenerator and LineItemGenerator.
D. HeaderGenerator and LineItemGenerator are Invoicer ports.
Answer: A
QUESTION 24
What is true about a pseudostate?
A. a state that can be specialized for different purposes
B. a state entry or exit point
C. a specification of a potential state
D. not a state but a vertex
Answer: D
QUESTION 25
A protocol state machine can be used to describe which aspect of a component?
A. internals of a component
B. signal flow among connectors
C. external contract of a component
D. configuration of an assembly
Answer: C
QUESTION 26
What is NOT a valid VariableAction?
A. RemoveVariableValueAction
B. AddVariableValueAction
C. ClearVariableAction
D. ReadVariableAction
E. SetVariableAction
Answer: E
A. A
B. B
C. C
D. D
Answer: C
A. either two p messages or two q messages
B. either p followed by q or q followed by p
C. only a p message followed by a q message
D. any combination of two p messages and two q messages
Answer: B
A. The OrderEntity component is part of the internals of the Invoicer component.
B. The Invoicer has a complex connector that connects the GenerateInvoice interface with the Order interface.
C. This is an illegal diagram.
D. The Invoicer has a complex port that provides the interface GenerateInvoice and requires the interface Order.
Answer: D
A. A
B. B
C. C
D. D
E. E
F. F
G. G
Answer: A.D.E
Get yourself composed for Microsoft actual exam and upgrade your skills with Flydumps OMG UM0-200 practice test products. Once you have practiced through our assessment material, familiarity on OMG https://www.pass4itsure.com/um0-200.html exam domains get a significant boost. Flydumps.com practice tests enable you to raise your performance level and assure the guaranteed success for OMG UM0-200 exam.